Provision of Pavement Materials & Pre-Coated Screenings Supply and deliver materials & Pre-Coated Screenings on Murgon-Gayndah Road Cloyna
25,000 tonne Type 2.1 Pavement material
20,000 tonne Type 2.3 Pavement material
1,000 tonne CBR 15 Select fill
200 tonne sand bedding material
325 tonne 10mm precoated screenings
450 tonne 14mm precoated screenings
RoadTek will award based on the best offer for each material type, hence there maybe more then one supplier under this contract of supply.
Construction works are programmed for commencement in June 2023.
It is intended that the paving materials excluding the screenings are carted into stockpile by August 2023.
Offerors are requested in their offer to provide an indicative timeframe for manufacture and delivery.